3 Pasig River Bridges Progress Update as of February 2020
Watch the latest progress update of the three ongoing bridge projects along Pasig River: BGC-Ortigas Bridge, Binondo-Intramuros Bridge, and Estrella Pantaleon Bridge.
According to Dmitri Valencia, for Binondo-Intramuros bridge, we saw a column visible at the Intramuros side with another rising up on the Binondo side.
As for Estrella-Pantaleon Bridge, there is a column visible on the Mandaluyong side. Developments along the Rockwell/Estrella side are also underway.
For BGC-Ortigas Bridge, nothing much happened at the Pasig side. You could see columns being erected along Lawton Avenue in Makati.
Two of the bridges are financed thru China ODA (Official Development Assistance), the Binondo-Intramuros Bridge and Estrella-Pantaleon Bridge.
China Aid Bridges –
Binondo Intramuros Bridge – 734 meter
Estrella Pantaleon Bridge replacement – 506 meters
Chinese contractor China Road and Bridge Corporation (CRBC) is in the country to help build the two bridges in Metro Manila.
BGC Ortigas bridge – 613.77meters – Persan Construction Inc. and Sino Road and Bridge Company Limited Inc.
DPWH says current status is at 45%
reference: xinhua news / Phil star / dpwh
Drone pilot: dmitrivalencia