Metro Manila Skyway Stage 3 Latest Aerial Inspection
The 18-kilometer Skyway Stage 3 was not completed using its original alignment, which was approved in 2014. Due to right-of-way difficulties, it had to be realigned following the San Juan River alignment. Have you seen the aerial inspection lately?
This was approved via a Memorandum of Agreement, which was signed on October 25, 2018. Prior to this, site possession for the entire project was only at 8.64 percent.
Video courtesy of Secretary Mark Villar