SLEX Toll Road 4 Progress Update as of February 2022
The ongoing works on SLEX-TR4 is currently focused on Section B in Alaminos, Laguna and Section C in Tiaong, Quezon, near Hacienda Escudero. Here’s the latest update of the SLEX Toll Road 4 as of February 2022.
Section B is concentrated on the project’s PNR underpass, Koquinkona bridge, and Maharlika underpass, all parallel to the Alaminos-Tiaong Bypass road. Pipe-laying for drainage as well as embankment works to level the road prior to laying of concrete, is also ongoing.
Meanwhile, at Section C, work on the Tiaong, Quezon interchange has also progressed well, according to Ang. Construction of the Tiaong bridge, Tiaong underpass, and Dolores bridge, as well as drainage and embankment works, are also underway.